Get Started
1035

Q: 9 girls working 7 hours a day can complete a piece of work in 15 day. In how many days can 6 girls working for 9 hours a day, complete the same piece of work?

  • 1
    35/4 days
  • 2
    17.5 days
  • 3
    19 3/4 days
  • 4
    37/3 days
  • Show Answer
  • Workspace

Answer : 2. "17.5 days"
Explanation :

Answer: B) 17.5 days Explanation: Let the number of days be 'p'  As the work is same, we know that M1 x D1 x H1 = M2 x D2 x H2 Where M = Men, D = Days, H = Hours per day  Here M1 = 9, D1 = 15, H1 = 7  M2 = 6, D2 = p, H2 = 9  => 9 x 15 x 7 = 6 x p x 9  => p = 35/2 = 17.5 days.

The Most Comprehensive Exam Preparation Platform

Get the Examsbook Prep App Today