8प्र: P and Q can complete a job in 24 days working together. P alone can complete it in 32 days. Both of them worked together for 8 days and then P left. The number of days Q will take to complete the remaining work is ? 3415 05b5cc6c0e4d2b4197774db05
5b5cc6c0e4d2b4197774db05- 156 daysfalse
- 254 daysfalse
- 360 daysfalse
- 464 daystrue
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 4. "64 days"
व्याख्या :
Answer: D) 64 days Explanation: (P+Q)'s 1 day work = 1/24 P's 1 day work = 1/32 => Q's 1 day work = 1/24 - 1/32 = 1/96 Work done by (P+Q) in 8 days = 8/24 = 1/3 Remainining work = 1 - 1/3 = 2/3 Time taken by Q to complete the remaining work = 2/3 x 96 = 64 days.
प्र: Which statement best describes an O3 molecule? 3412 05b5cc6b3e4d2b4197774d432
5b5cc6b3e4d2b4197774d432- 1The double bond in ozone switches back and forth between the two outer oxygen atomsfalse
- 2An ozone molecule contains one single bond and one double bondtrue
- 3Each atom in ozone is connected to another atom by 1.5 bonds.false
- 4Nonefalse
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 2. "An ozone molecule contains one single bond and one double bond"
व्याख्या :
Answer: B) An ozone molecule contains one single bond and one double bond Explanation: Ozone molecule has one single bond and one double bond.
प्र: The longest ship canal in the world is the 3407 05b5cc69fe4d2b4197774c9fb
5b5cc69fe4d2b4197774c9fb- 1Suez canal, Egyptfalse
- 2Kiel canal, Germanyfalse
- 3Panama canal, Central Americafalse
- 4St. Laurence Seaway (USA and Canada)true
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 4. "St. Laurence Seaway (USA and Canada)"
व्याख्या :
Answer: D) St. Laurence Seaway (USA and Canada) Explanation:
प्र: A batsman in his 17th innings makes a score of 85 and their by increasing his average by 3. What is his average after the 17th innings ? 3400 05b5cc6e9e4d2b4197774ee01
5b5cc6e9e4d2b4197774ee01- 134false
- 236false
- 335false
- 437true
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 4. "37"
व्याख्या :
Answer: D) 37 Explanation: 16x + 85 = 17(x + 3) x = 34 + 3 = 37
प्र: If NAMO = 172 and OM = 56 then, SHIVAY = ? 3390 05b5cc6cee4d2b4197774e237
5b5cc6cee4d2b4197774e237- 1606false
- 2415false
- 3504true
- 4404false
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 3. "504"
व्याख्या :
Answer: C) 504 Explanation: (COUNTING OF LETTERS) NAMO = 14 + 1 + 13 + 15 = 43 x 4 = 172, OM = 15 + 13 = 28 x 2 = 56, SHIVAY = 19 + 8 + 9 + 22 + 1 + 25 = 84 x 6 = 504
प्र: From the following pairs, find the one which is correctly matched? 3385 05b5cc6bee4d2b4197774d960
5b5cc6bee4d2b4197774d960- 1Scurvy- Thiaminefalse
- 2Tuberculosis- ATSfalse
- 3Tetanus- BCGfalse
- 4Malaria- Chloroquinetrue
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 4. "Malaria- Chloroquine"
व्याख्या :
Answer: D) Malaria- Chloroquine Explanation: Chloroquine is a medication used to prevent and to treat malaria.
प्र: The wildcard in a WHERE clause is useful when 3384 05b5cc65ee4d2b4197774be3b
5b5cc65ee4d2b4197774be3b- 1An exact match is not possible in a SELECT statement.true
- 2An exact match is necessary in a CREATE statement.false
- 3An exact match is not possible in a CREATE statement.false
- 4An exact match is necessary in a SELECT statement.false
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 1. "An exact match is not possible in a SELECT statement."
व्याख्या :
Answer: A) An exact match is not possible in a SELECT statement. Explanation:
प्र: In a regular week, there are 5 working days and for each day, the working hours are 8. A man gets Rs. 2.40 per hour for regular work and Rs. 3.20 per hours for overtime. If he earns Rs. 432 in 4 weeks, then how many hours does he work for ? 3380 05b5cc74fe4d2b4197774fb35
5b5cc74fe4d2b4197774fb35- 1145false
- 2165false
- 3175true
- 4135false
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 3. "175"
व्याख्या :
Answer: C) 175 Explanation: Given that, working days = 5 working hours = 8 A man get rupess per hour is Rs.2.40 So in one day the man get total rupees is 2.40 x 8 = 19.2 So in 5 days week the man get total rupees is 19.2 x 5 = 96 So in 4 week the man get total rupees is 96 x 4 = 384 So the man worked for = 160hours in 4 weeks But given that the man earned Rs.432 Hence remaning money is (432-384 = 48)which is earn by doing overtime work Overtime hours = 48/3.20 = 15 So total worked hours is = 15 + 160 = 175.