Q: Three strategies P, Q and R have been initiated for cost cutting in a company producing respectively 20%, 30% and 10% savings. Assuming that they operate independently, what is the net saving achieved ? 2624 0

  • 1
    49.6%
    Correct
    Wrong
  • 2
    50.4%
    Correct
    Wrong
  • 3
    33.67%
    Correct
    Wrong
  • 4
    66.66%
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "49.6%"
Explanation :

Answer: A) 49.6% Explanation: As these three strategies P, Q and R are independent so these will cut cost one after the other.If initial cost is Rs 100, then20% cost is cut after initializing strategy P, then cost will remain 80% = 80further 30% cost is cut after strategy Q, then cost will remain 70% of 80 = 56further 10% cost is cut after strategy R, then cost will remain 90% of 56 = 50.4 Thus final cost remains 50.4 % of the original cost. Hence net saving is 100 - 50.4 = 49.6 %.

Q: The top and bottom of a tower were seen to be at angles of depression 30° and 60° from the top of a hill of height 100 m. Find the height of the tower ? 2618 1

  • 1
    42.2 mts
    Correct
    Wrong
  • 2
    33.45 mts
    Correct
    Wrong
  • 3
    66.6 mts
    Correct
    Wrong
  • 4
    58.78 mts
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "66.6 mts"
Explanation :

Answer: C) 66.6 mts Explanation: From above diagramAC represents the hill and DE represents the tower Given that AC = 100 m angleXAD = angleADB = 30° (∵ AX || BD ) angleXAE = angleAEC = 60° (∵ AX || CE) Let DE = h Then, BC = DE = h, AB = (100-h) (∵ AC=100 and BC = h), BD = CE tan 60°=AC/CE => √3 = 100/CE =>CE = 100/√3 ----- (1) tan 30° = AB/BD => 1/√3 = 100−h/BD => BD = 100−h(√3)∵ BD = CE and Substitute the value of CE from equation 1 100/√3 = 100−h(√3) => h = 66.66 mts The height of the tower = 66.66 mts.

Q: 25% of 25% Is Equal To 2617 0

  • 1
    0.0625
    Correct
    Wrong
  • 2
    0.0210
    Correct
    Wrong
  • 3
    0.03145
    Correct
    Wrong
  • 4
    0.3210
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "0.0625"
Explanation :

Answer: A) 0.0625 Explanation: 25% of 25% means   25/100 of 25/100   i.e, 1/4 of 1/4   or in other words 1/4 x 1/4=1/16   Hence, the answer is 1/16 = 0.0625.

Q: What will be the cost of building a fence around a square plot with area equal to 289 sq ft, if the price per foot of building the fence is Rs. 58 ? 2608 0

  • 1
    Rs. 3748
    Correct
    Wrong
  • 2
    Rs. 3847
    Correct
    Wrong
  • 3
    Rs. 3944
    Correct
    Wrong
  • 4
    Rs. 3154
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "Rs. 3944"
Explanation :

Answer: C) Rs. 3944 Explanation: Let the side of the square plot be 'a' ft.Given area of the plot (a x a) = 289 => a = 17Length of the fence = Perimeter of the plot = 4a = 68 ft.Cost of building the fence = 68 x 58 = Rs. 3944.

Q: Find the next number in the given series 0.25, 8, 128, 1024, ? 2608 0

  • 1
    4096
    Correct
    Wrong
  • 2
    2526
    Correct
    Wrong
  • 3
    8486
    Correct
    Wrong
  • 4
    2620
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "4096"
Explanation :

Answer: A) 4096 Explanation: Here given series follows a pattern that 0.25, 8, 128, 1024, ? 0.25 x 32 = 8 8 x 16 = 128 128 x 8 = 1024 1024 x 4 = 4096

Q: If the sum of two numbers is 55 and the H.C.F. and L.C.M. of these numbers are 5 and 120 respectively, then the sum of the reciprocals of the numbers is equal to ? 2604 0

  • 1
    13/125
    Correct
    Wrong
  • 2
    14/57
    Correct
    Wrong
  • 3
    11/120
    Correct
    Wrong
  • 4
    16/41
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "11/120"
Explanation :

Answer: C) 11/120 Explanation: Let the numbers be a and b.We know that product of two numbers = Product of their HCF and LCMThen, a + b = 55 and ab = 5 x 120 = 600.=> The required sum = (1/a) + (1/b) = (a+b)/ab=55/600 = 11/120

Q: A boat takes 2 hours to travel from point A to B in still water. To find out its speed upstream, which of the following information is/are required? A. Distance between point A and B. B. Time taken to travel downstream from B to A. C. Speed of the stream of water. 2604 0

  • 1
    Only A and B
    Correct
    Wrong
  • 2
    Only B and C
    Correct
    Wrong
  • 3
    All are required
    Correct
    Wrong
  • 4
    Any one pair of A and B, B and C or C and A is sufficient
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "Any one pair of A and B, B and C or C and A is sufficient"
Explanation :

Answer: D) Any one pair of A and B, B and C or C and A is sufficient Explanation: Let distance between A & B = d kmLet speed in still water = x kmphLet speed of current = y kmph from the given data,d/x = 2 From A) we get dFrom B) we get d/x+yFrom C) we get y   So, Any one pair of A and B, B and C or C and A is sufficient to give the answer i.e, the speed of upstream.

Q: 88 cubic centimetres of silver is drawn into a wire 1 mm in diameter. The length of the wire in metres will be ? 2604 0

  • 1
    112 mts
    Correct
    Wrong
  • 2
    84 mts
    Correct
    Wrong
  • 3
    96 mts
    Correct
    Wrong
  • 4
    108 mts
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 2. "84 mts"
Explanation :

Answer: B) 84 mts Explanation: Vol of silver = πR2h  = 66 C.C   Given D= 1mm => R = D/2 = 1/20 cm     => 227×1202×h = 66 = 66 x 400 x (7/22) = 8400 cm = 84 mtrs.

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully