Quantitative Aptitude Practice Question and Answer

Q: What number should replace the question mark? 125, 138, 164, ?, 255 2529 0

  • 1
    189
    Correct
    Wrong
  • 2
    197
    Correct
    Wrong
  • 3
    200
    Correct
    Wrong
  • 4
    203
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 4. "203"
Explanation :

Answer: D) 203 Explanation: The given number series is 125,   138,   164,   ?,   255   125   125 + 13x1 = 138   138 + 13x2 = 164   164 + 13x3 = 203   203 + 13x4 = 255       Hence, the missing number in the series is 203.

Q: If 15% of x = 20% of y, then x:y is  ___? 2521 0

  • 1
    4:3
    Correct
    Wrong
  • 2
    5:4
    Correct
    Wrong
  • 3
    4:5
    Correct
    Wrong
  • 4
    3:4
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "4:3"
Explanation :

Answer: A) 4:3 Explanation: Given 15% of x = 20% of y => 15x = 20y => x/y = 20/15 => x : y = 4 : 3

Q: The top and bottom of a tower were seen to be at angles of depression 30° and 60° from the top of a hill of height 100 m. Find the height of the tower ? 2519 1

  • 1
    42.2 mts
    Correct
    Wrong
  • 2
    33.45 mts
    Correct
    Wrong
  • 3
    66.6 mts
    Correct
    Wrong
  • 4
    58.78 mts
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "66.6 mts"
Explanation :

Answer: C) 66.6 mts Explanation: From above diagramAC represents the hill and DE represents the tower Given that AC = 100 m angleXAD = angleADB = 30° (∵ AX || BD ) angleXAE = angleAEC = 60° (∵ AX || CE) Let DE = h Then, BC = DE = h, AB = (100-h) (∵ AC=100 and BC = h), BD = CE tan 60°=AC/CE => √3 = 100/CE =>CE = 100/√3 ----- (1) tan 30° = AB/BD => 1/√3 = 100−h/BD => BD = 100−h(√3)∵ BD = CE and Substitute the value of CE from equation 1 100/√3 = 100−h(√3) => h = 66.66 mts The height of the tower = 66.66 mts.

Q: The product of two positive numbers is p. If each of the numbers is increased by 2, the new product is how much greater than twice the sum of the two original numbers ? 2516 0

  • 1
    p times
    Correct
    Wrong
  • 2
    2p times
    Correct
    Wrong
  • 3
    (p + 4) times
    Correct
    Wrong
  • 4
    (2p + 3) times
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "(p + 4) times"
Explanation :

Answer: C) (p + 4) times Explanation: Let the two no's be a and b;Given product of the no's is p = ab;If the each nos is increased by 2 then the new product will be (a+2)(b+2) = ab + 2a + 2b + 4= ab + 2(a+b) + 4= p + 2(a+b) + 4Hence the new product is (p+4) times greater than twice the sum of the two original numbers.

  • Show AnswerHide Answer
  • Workspace

Answer : 1. "4/3 days"
Explanation :

Answer: A) 4/3 days Explanation: Let the total number of documents to be printed be 12.  The number of documents printed by P in 1 day = 4.  The number of documents printed by Q in 1 day = 3.  The number of documents printed by R in 1 day = 2.  Thus, the total number of documents that can be printed by all the machines working simultaneously in a single day = 9.   Therefore, the number of days taken to complete the whole work = 12/9 = 4/3 days.

Q: The average temperature for Monday, Tuesday, Wednesday and Thursday was 48 degrees and for Tuesday, Wednesday, Thursday and Friday was 46 degrees. If the temperature on Monday was 42 degrees. Find the temperature on Friday ? 2511 0

  • 1
    34
    Correct
    Wrong
  • 2
    36
    Correct
    Wrong
  • 3
    38
    Correct
    Wrong
  • 4
    40
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "34"
Explanation :

Answer: A) 34 Explanation: M + Tu + W + Th = 4 x 48 = 192Tu + W + Th + F = 4 x 46 = 184M = 42Tu + W + Th = 192 - 42 = 150F = 184 – 150 = 34

Q: What will be the cost of building a fence around a square plot with area equal to 289 sq ft, if the price per foot of building the fence is Rs. 58 ? 2511 0

  • 1
    Rs. 3748
    Correct
    Wrong
  • 2
    Rs. 3847
    Correct
    Wrong
  • 3
    Rs. 3944
    Correct
    Wrong
  • 4
    Rs. 3154
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 3. "Rs. 3944"
Explanation :

Answer: C) Rs. 3944 Explanation: Let the side of the square plot be 'a' ft.Given area of the plot (a x a) = 289 => a = 17Length of the fence = Perimeter of the plot = 4a = 68 ft.Cost of building the fence = 68 x 58 = Rs. 3944.

Q: A motorboat goes 8 km an hour in still water, but takes thrice as much time in going the same distance against the current than going with the current. Then find the speed of the current? 2510 0

  • 1
    4 kmph
    Correct
    Wrong
  • 2
    6 kmph
    Correct
    Wrong
  • 3
    3 kmph
    Correct
    Wrong
  • 4
    2 kmph
    Correct
    Wrong
  • Show AnswerHide Answer
  • Workspace

Answer : 1. "4 kmph"
Explanation :

Answer: A) 4 kmph Explanation: Let the speed of current = 'C' km/hr   Given the speed of boat in still water = 6 kmph   Let 'd' kms be the distance it covers.   According to the given data,   Boat takes thrice as much time in going the same distance against the current than going with the current   i.e, d8 - C = 3 × d8 + C   ⇒ 24 - 3C = 8 + C⇒ 4C = 16⇒ C = 4 kmph   Hence, the speed of the current C = 4 kmph.

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully

      Report Error

    Please Enter Message
    Error Reported Successfully