8प्र: A project charter is one of the key deliverables to come from the initiation process. The project charter should by issued by 1338 05b5cc7cce4d2b41977751067
5b5cc7cce4d2b41977751067- 1one or more functional managersfalse
- 2The head of the performing organizationfalse
- 3A manager external to the projecttrue
- 4The CFOfalse
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 3. "A manager external to the project"
व्याख्या :
Answer: C) A manager external to the project Explanation: The other answers could be accurate in specific situations, but their role alone does not meet the keyb criterion of being "external" to the project team. Answers A, B, and D are incorrect because these individuals are not external to the project.
प्र: Project authorization is one of the processes that is associated with the initiation phase of a project. Authorization can come in many different forms, and projects are generally authorized by all of the following except 1448 05b5cc7cce4d2b41977751062
5b5cc7cce4d2b41977751062- 1Technological Advancesfalse
- 2Customer request or market demandfalse
- 3Executive year - end bonusestrue
- 4Business or Social needsfalse
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 3. "Executive year - end bonuses"
व्याख्या :
Answer: C) Executive year - end bonuses Explanation: Project authorization should not be exclusively based upon the impact of an executive's bonus (many people would agree that it should not ever be based upon an executive's bonus). Answer A, B, and D are common events that predicate the need for project authorization and can evolve into large scope projects.
प्र: Subject matters experts (SMEs) are resources that are imperative to the succes of a project. Many times, project managers are not experts in the areas they are managing and frequently must rely upon other's expertise. In which scope - management process are SMEs first used? 1313 05b5cc7cce4d2b4197775105d
5b5cc7cce4d2b4197775105d- 1Scope planningfalse
- 2Scope definitionfalse
- 3Initiationtrue
- 4Scope verificationfalse
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 3. "Initiation"
व्याख्या :
Answer: C) Initiation Explanation: Initiation is the first step in the scope management process, and expert judgment is one of the techniques routinely utilized. Answers A, B, and D are incorrect because they would come after the initiation process.
प्र: You are a project manager for the redevelopment of the Hoover Dam. Your team has been provided with the scope statement, but it lacks many description details. Your team is concerned because the project is in the initiation phase and it wants to postpone it until it has more information. As the project manager, you recommend that 1389 05b5cc7cce4d2b41977751058
5b5cc7cce4d2b41977751058- 1The team should go forward, but be caution about the lack of details and the impact upon the timeline for the projectfalse
- 2The project should not go forward until the stakeholders agree about the scope and purpose of the projectfalse
- 3The team should verify the scope and realize that more details will be available as more project characteristics are progressively elaborated.true
- 4The team should review the project selection criteria for the Hoover Dam projectfalse
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 3. "The team should verify the scope and realize that more details will be available as more project characteristics are progressively elaborated."
व्याख्या :
Answer: C) The team should verify the scope and realize that more details will be available as more project characteristics are progressively elaborated. Explanation: The project details and description will usually have less detail at the beginning of the project and will increase as the characteristics are progressively elaborated. Answer A is incorrect because the team should confirm that they understand the esence of the scope of the project, even if the details might be ambiguous at the beginning of the project. Answer B is incorrect because the project should go forward; however, the team should request further clarification of what the project scope entails. Answer D is incorrect because the project selection criteria should be established before the project begins.
प्र: A Good CFO will tell you that it is important to look at your bottom line and determine how to increase profits for the organization. Veronica, the new CFO at a local university, is taking that approach and applying it to new projects. Therefore,she wants to include costs from each phase of the project on a total expenditure is known as 1382 05b5cc7cce4d2b41977751053
5b5cc7cce4d2b41977751053- 1An opportunity costfalse
- 2A sunk costfalse
- 3NPVfalse
- 4A life cycletrue
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 4. "A life cycle"
व्याख्या :
Answer: D) A life cycle Explanation: Life Cycle costing includes the costs from each phase of the project life cycle when the total investment costs are calculated. Answer A is incorrect because an opportunity cost is the difference between a chosen investment and the one that is passed up. Answer B is incorrect because sunk costs are costs that have been incurred and cannot be reversed. Answer C is incorrect because net present value (NPV) is the present value of cash inflows(benifits) minus the present value of cash outflows (costs).
प्र: You are working on a new project to develop a new wireless product with ease - of - use features recommended by customers. It is as yet undetermined which features and the extent to which each feature will be incorporated into the product.You have a focus group that will continue to evaluate the features as the project goes forward.The focus group is authorized to suggest changes, as are your engineers and the quality department.As a project manager, what will help you most to minimize the effect of these changes? 1700 05b5cc7cce4d2b4197775104e
5b5cc7cce4d2b4197775104e- 1A change management planfalse
- 2A scope management plantrue
- 3Do not continue with the project until all of the features are clearly defined in the scope statement and scope definition.false
- 4This is an expected part of every project. A good project manager will have a communications plan in place to be sure everyone knows what is happening on the project.false
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 2. "A scope management plan"
व्याख्या :
Answer: B) A scope management plan Explanation: Answer A is tempting because the problem focuses on changes. However, because we are talking about the elaboration of the product's characteristics, we are talking about scope changes, and therefore Answer B is the best answer. Answer C is also tempting because it is difficult to more forward on a project until the scope is clearly defined (especially in systems development projects), but with products and certain types of web development, scope changes can be frequent, and a formal scope management plan is needed. Answer D is true from a project perspective, but does not addres the scope issues.
प्र: Your company has a policy of having every software project reviewed and approved by the Architecture Review Board prior to the construction phase of a project. you are currently in the process of activity sequencing. This is a example of what? 1350 05b5cc7cce4d2b41977751049
5b5cc7cce4d2b41977751049- 1Gatekeepingfalse
- 2Milestonetrue
- 3New scope for the projectfalse
- 4Project integrationfalse
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 2. "Milestone"
व्याख्या :
Answer: B) Milestone Explanation: The approval by the Architecture Review Board is a milestone you want to include in activity sequencing so that you can ensure the requirements for meeting the review board's approval are met. Answer A is tempting because the question references phase-end activities; however, it is not an example of gatekeeping because the project is not being authorized to continue based only on the architecture review.Gatekeeping often involves the review of other factors as well. Answer C is incorect because the requirement of a review board approval does not afect scope. Answer D is incorrect because project integration planning involves project plan development, execution, and integrated change control, which are not related to a review board.
प्र: On a systems development project, Richard needs two programmers. He knows John and Smith were able to create a program in 40 days similar to the one he wants to create on his project. He decides to use 40 days as his estimate. This is an example of what type of estimating? 1438 05b5cc7cce4d2b41977751044
5b5cc7cce4d2b41977751044- 1Parametric modelingfalse
- 2Analogoustrue
- 3Rule of thumbfalse
- 4Fixed Ratefalse
- उत्तर देखेंउत्तर छिपाएं
- Workspace
- SingleChoice
उत्तर : 2. "Analogous"
व्याख्या :
Answer: B) Analogous Explanation: Richard is using an estimate based on a project very similar to to his own with staff he will be using. Answer A is incorrect because perametric modeling involves using a mathematical model to predict costs, such as dollars per line of code. Answer C is incorrect, although close; if the development project is a common item, such as putting down new flooring, a rule -of-thumb measurement can be used, although it is less accurate. Answer D is incorrect because it is not a form of estimating, but a type of pricing.