प्र: Project Procurement Management - Processes Describe the Inputs, Tools and Techniques , Outputs included in the Contract Administration?

  • उत्तर देखेंउत्तर छिपाएं
  • Workspace

उत्तर :
व्याख्या :

I. Inputs Contract Contract management plan Selected sellers Performance reports Approved change requests Work performance information II. Tools and Techniques Contract change control system Buyer-conducted performance review Inspections and audits Performance reporting Payment system Claims administration Records management system Information technology III. Outputs Contract documentation  Requested changes Recommended corrective actions Organizational process assets (updates) Project management plan (updates)                  - Procurement management plan                  - Contract management plan