Q: Project Procurement Management - Processes Describe the Inputs, Tools and Techniques , Outputs included in the Plan Contracting?

  • Show AnswerHide Answer
  • Workspace

Answer :
Explanation :

I. Inputs Procurement management plan Contract statement of work Make-or-buy decisions Project management plan                  - Risk register                  - Risk related contractual agreements                  - Resource requirements                  - Project schedule                  - Activity cost estimate                  - Cost baseline II. Tools and Techniques Standard forms Expert judgment III. Outputs Procurement documents Evaluation criteria Contract statement of work (updates)