जॉइन Examsbookउत्तर :
Project Time Management - Processes
Describe the Inputs, Tools and Techniques, Outputs of Activity Duration Estimating ?5
प्र: Project Time Management - Processes Describe the Inputs, Tools and Techniques, Outputs of Activity Duration Estimating ?
- उत्तर देखेंउत्तर छिपाएं
- Workspace
उत्तर :
व्याख्या :
I. Inputs Enterprise environmental factors Organizational process assets Project scope statement Activity list Activity attributes Activity resource requirements Resource calendars Project management plan - Risk register - Activity cost estimates II. Tools and Techniques Expert judgment Analogous estimating Parametric estimating Three-point estimates Reserve analysis III. Outputs Activity duration estimates Activity attributes (updates)