प्र: The triple constraints of Project Management are frequently discussed in other contextx such as marketing classes and a variety of other subjects. The interaction between _____, ______, and _______can be seen as a triangle, with the three sides impacting the others.

  • 1
    quality, resources, time
  • 2
    money, resources, quality
  • 3
    scope, quality, planning
  • 4
    time, scope, cost
  • उत्तर देखेंउत्तर छिपाएं
  • Workspace

उत्तर : 4. "time, scope, cost"
व्याख्या :

Answer: D) time, scope, cost Explanation: Scope, quality, and cost are the triple constraints. Quality is a function of these three areas and can impact them; however it is not considered one of the components of the triple constraint. Therefore, Answer A, B, and C are incorect.