A is 40% more efficient than C and B is 50% more efficient than A. If A and C together can complete a piece of work in 45 days, then find days taken by A, B & C together to complete 50% of the work?

  • 1
    20 दिन
  • 2
    24 दिन
  • 3
    26 दिन
  • 4
    32 दिन
  • 5
    16 दिन
  • उत्तर देखें
  • Workspace

Answer : 2. "24 दिन"