प्र: Iam looking to estimate the cost on a project, but I don't want to spend a lot of time on a  detailed analysis. I really want a ballpark figure. What options do I have? 1456 0

  • 1
    None - Cost estimating requires details to be accurate
    सही
    गलत
  • 2
    Use the cost of similar projects
    सही
    गलत
  • 3
    Use a rule-of-thumb or per-square-foot estimate
    सही
    गलत
  • 4
    Add up the costs on the WBS
    सही
    गलत
  • उत्तर देखेंउत्तर छिपाएं
  • Workspace

उत्तर : 2. "Use the cost of similar projects"
व्याख्या :

Answer: B) Use the cost of similar projects Explanation: Although it is less accurate than adding up individual costs from the WBS, it is less time consuming. The trade-off is accuracy. Answer A is incorrect because to do a more accurate cost estimate, you need to delve into details. Answer C is tempting also, and possible, except we don't really know if the project in question can use perametric modeling . Answer D is incorrect because it takes the most time, but it is most accurate.

प्र: Why are risk tolerances and thresholds important to identify in the risk management Plan? 1304 0

  • 1
    Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution
    सही
    गलत
  • 2
    Tolerances and thresholds help to define how often the risk management process will be performed
    सही
    गलत
  • 3
    Tolerances and thresholds determine what tools and data sources will be used in risk management
    सही
    गलत
  • 4
    Tolerances and thresholds provide the basis for costing the risk management process as well as defining how risk activities will be recorded
    सही
    गलत
  • उत्तर देखेंउत्तर छिपाएं
  • Workspace

उत्तर : 1. "Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution"
व्याख्या :

Answer: A) Tolerances and thresholds, when documented, can help to define the target by which the project team can measure the effectiveness of the risk response plan execution Explanation: Answer B defines the timing that should be addressed in the risk management plan. Answer C defines the methodology that should be identified in a risk management plan. Answer D touches on the budgeting and tracking that should be defined in the risk management plan.

प्र: Why are CPM, GERT, and PERT not considered sufficient to create a project schedule? 1812 0

  • 1
    All three are tools and techniques of schedule development, not the actual schedule
    सही
    गलत
  • 2
    As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations
    सही
    गलत
  • 3
    They are sufficient. Each calculates early and late start and finish dates for each activity
    सही
    गलत
  • 4
    They are Monte Carlo techniques used to provide what-if analysis for adverse external factors on a project
    सही
    गलत
  • उत्तर देखेंउत्तर छिपाएं
  • Workspace

उत्तर : 2. "As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations"
व्याख्या :

Answer: B) As mathemetical analysis tools, they simply provide the dates that are posible, and do not consider resource pool limitations Explanation: Answer A is tempting because it is true by definition, but Answer B is correct because it properly answers the question, in that these techniques do not take into account resource pool constraints. Answer C is incorrect because it provides possible early and late start and finish dates, but not the actual schedules. Answer D is incorrect because none of the the three are simulation techniques.

प्र: Decomposing tasks into smaller activities can be helpful in reducing the amount of stress associated with overwhelmingly large milestones. What is a feature of the hierarchical nature of the WBS? 1286 0

  • 1
    A WBS hierarchy prevents duplication
    सही
    गलत
  • 2
    A WBS cab be rolled up or collapsed to provide information at the appropriate level for a particular audience.
    सही
    गलत
  • 3
    The decomposition of tasks provides a detailed planning tool
    सही
    गलत
  • 4
    The depth of a WBS is restricted to three levels, which avoids overplanning
    सही
    गलत
  • उत्तर देखेंउत्तर छिपाएं
  • Workspace

उत्तर : 2. "A WBS cab be rolled up or collapsed to provide information at the appropriate level for a particular audience."
व्याख्या :

Answer: B) A WBS cab be rolled up or collapsed to provide information at the appropriate level for a particular audience. Explanation: Answer A is incorrect because the WBS hierarchy does not prevent duplication by itself. Answer C is incorrect because a WBS is focused on deliverables and components or work packages and not on tasks. Answer D is incorrect because a WBS can be sized appropriately to the project size with as many levels as necessary.

प्र: Why static methods cannot access non static variables or methods? 1587 0

  • उत्तर देखेंउत्तर छिपाएं
  • Workspace

उत्तर :
व्याख्या :

A static method cannot access non static variables or methods because static methods doesnt need the object to be accessed. So if a static method has non static variables or non static methods which has instantiated variables they will no be intialized since the object is not created and this could result in an error.

प्र: Two greatest Buddhist universities of Nalanda and Vikramshila were patronised by the 1539 0

  • 1
    Palas
    सही
    गलत
  • 2
    Paramaras
    सही
    गलत
  • 3
    Chandelas
    सही
    गलत
  • 4
    All the above
    सही
    गलत
  • उत्तर देखेंउत्तर छिपाएं
  • Workspace

उत्तर : 1. "Palas"
व्याख्या :

Answer: A) Palas Explanation:

प्र: The oldest specimens of poetry in the punjabi language are devotional compositions attributed to 1829 0

  • 1
    Guru Nanak
    सही
    गलत
  • 2
    Baba Farid
    सही
    गलत
  • 3
    Guru Angad
    सही
    गलत
  • 4
    Guru Tegh Bahadur
    सही
    गलत
  • उत्तर देखेंउत्तर छिपाएं
  • Workspace

उत्तर : 2. "Baba Farid"
व्याख्या :

Answer: B) Baba Farid Explanation:

प्र: Who of the following Portuguese is regarded as a 'monster in human disguise' and the one who had no bowels of compassion? 2178 0

  • 1
    Vasco da Gama
    सही
    गलत
  • 2
    Albuquerque
    सही
    गलत
  • 3
    Almeida
    सही
    गलत
  • 4
    Joao de Castro
    सही
    गलत
  • उत्तर देखेंउत्तर छिपाएं
  • Workspace

उत्तर : 1. "Vasco da Gama"
व्याख्या :

Answer: A) Vasco da Gama Explanation:

      त्रुटि की रिपोर्ट करें

    कृपया संदेश दर्ज करें
    त्रुटि रिपोर्ट सफलतापूर्वक जमा हुई

      त्रुटि की रिपोर्ट करें

    कृपया संदेश दर्ज करें
    त्रुटि रिपोर्ट सफलतापूर्वक जमा हुई

      त्रुटि की रिपोर्ट करें

    कृपया संदेश दर्ज करें
    त्रुटि रिपोर्ट सफलतापूर्वक जमा हुई

      त्रुटि की रिपोर्ट करें

    कृपया संदेश दर्ज करें
    त्रुटि रिपोर्ट सफलतापूर्वक जमा हुई

      त्रुटि की रिपोर्ट करें

    कृपया संदेश दर्ज करें
    त्रुटि रिपोर्ट सफलतापूर्वक जमा हुई

      त्रुटि की रिपोर्ट करें

    कृपया संदेश दर्ज करें
    त्रुटि रिपोर्ट सफलतापूर्वक जमा हुई

      त्रुटि की रिपोर्ट करें

    कृपया संदेश दर्ज करें
    त्रुटि रिपोर्ट सफलतापूर्वक जमा हुई

      त्रुटि की रिपोर्ट करें

    कृपया संदेश दर्ज करें
    त्रुटि रिपोर्ट सफलतापूर्वक जमा हुई